Mammoet Completes BMU Replacement Project in The Hague Using Liebherr LTM 11200
- Meagan Wood

- Mar 19
- 3 min read
30-Second Takeaway
Mammoet has successfully completed a complex BMU replacement project in The Hague, lifting components up to 3,500kg using a Liebherr LTM 11200 mobile crane. Despite limited space and nearby infrastructure constraints, the project was delivered safely with minimal disruption through careful planning and efficient crane deployment.

Mammoet completes complex urban lifting project in The Hague
Heavy lift specialist Mammoet has completed the replacement of roof-mounted Building Maintenance Units (BMUs) on two Dutch government buildings in The Hague.
The project, delivered in collaboration with Façade Access Solutions, part of the Alimak Group, involved lifting and installing multiple components ranging from 200kg to 3,500kg.
Liebherr LTM 11200 enables efficient single-position lifting
A key element of the project was the use of a Liebherr LTM 11200 mobile crane, equipped with a Y-frame system to enhance lifting performance and stability.
The Liebherr LTM 11200 provided up to 180 metres of lifting capability, allowing the crane to operate from a single position while servicing both buildings. This eliminated the need for crane relocation, significantly reducing disruption and improving overall project efficiency.
Its compact footprint also proved essential for working within the confined conditions of the city centre.
Overcoming tight urban constraints
The project presented several logistical challenges, including extremely limited working space and the presence of surrounding infrastructure such as a nearby viaduct. To manage these constraints, lifting operations were carefully organised into defined zones, ensuring an efficient workflow throughout the installation process. Components were installed in a planned sequence, enabling simultaneous assembly on the rooftops, further optimising project timelines.
Minimising disruption in a busy city centre
Given the project’s location in a central government district, minimising disruption was a priority. Road closures were limited to just one day, while the ability of the Liebherr LTM 11200 to handle all lifts from a single setup helped avoid additional traffic and logistical complications. This approach allowed Mammoet to maintain operational efficiency while respecting the constraints of a busy urban environment.
Strict safety measures implemented
Comprehensive safety protocols were implemented throughout the project, including the use of fixed lifting points, adherence to low wind speed limits, and the installation of crash decks to protect the buildings. Despite the complexity of working in a densely populated political centre, the project was completed safely and efficiently.
Demonstrating expertise in urban heavy lifting
The successful completion of the BMU replacement highlights Mammoet’s capability in delivering complex urban lifting projects, particularly in environments where space, safety, and logistics must be carefully balanced.The use of the Liebherr LTM 11200 played a central role in ensuring precision, efficiency, and minimal disruption throughout the operation.
About
About Mammoet
Mammoet is a global leader in heavy lifting and transport solutions, specialising in engineered lifting, transport, and installation services for large-scale infrastructure and industrial projects. The company is known for delivering complex operations in challenging environments worldwide.
Website: https://www.mammoet.com
About Liebherr
Liebherr is a global manufacturer of construction machinery and lifting equipment, including mobile cranes, crawler cranes, and tower cranes. The company is recognised for innovation in high-capacity lifting solutions such as the LTM 11200.
Website: https://www.liebherr.com
About Alimak Group
Alimak Group is a global provider of vertical access solutions, including façade access systems, construction hoists, and industrial elevators. Its Façade Access Solutions division specialises in BMUs and building maintenance systems.
Website: https://www.alimakgroup.com
Frequently Asked Questions
What is the Liebherr LTM 11200 used for?
The Liebherr LTM 11200 is a high-capacity mobile crane used for heavy lifting applications, including complex urban projects and infrastructure installations.
What was Mammoet’s project in The Hague?
Mammoet replaced roof-mounted Building Maintenance Units (BMUs) on two Dutch government buildings, lifting components weighing up to 3,500kg.
Why was the LTM 11200 chosen for this project?
The Liebherr LTM 11200 was selected for its long reach, high capacity, and ability to operate from a single position, making it ideal for confined urban environments.
What challenges did the project face?
The project involved limited space, nearby infrastructure such as a viaduct, and working in a busy city centre, requiring careful planning and coordination.
How did Mammoet minimise disruption?
Mammoet limited road closures to one day, used a single crane setup, and organised lifting operations efficiently to reduce impact on the surrounding area.