top of page

Wiesbauer lifts 100-tonne steel plates onto the new Neckar valley bridge with Liebherr LR 1700-1.0 and LTM 1650-8.1

–         Tandem lifts with radii of up to 96 metres

–         Steel sheets reinforce bridge construction

–         Modern Liebherr crane technology enables operations in confined spaces


Wiesbauer uses two Liebherr cranes to lift reinforcing plates onto the carriageway of the Horb high bridge at a height of 65 metres.
Wiesbauer uses two Liebherr cranes to lift reinforcing plates onto the carriageway of the Horb high bridge at a height of 65 metres.

High above the Neckar valley, an impressive project is currently under construction: as part of the new Horb bypass, the Karlsruhe Regional Council is building a 667 metre long and around 65 metre high bridge, which will carry the B32 federal road over the Neckar in future. Two Liebherr cranes from Wiesbauer GmbH & Co. KG - an LR 1700-1.0 crawler crane and an LTM 1650-8.1 mobile crane - were used to install solid steel plates on the underside of the two carriageway spans.


Ehingen (Donau) (Germany), 27 October 2025 - The demanding lifts required not only the highest precision, but also a high degree of planning and experience. The bridge over the Neckar Valley is designed as an "extra-dosed" bridge - a modern type of construction that combines elements of a cable-stayed and prestressed concrete bridge. They are characterised by their comparatively low pylons. The Horb bridge is also characterised by slender concrete footbridges, which give the bridge a graceful appearance. To ensure that these can still absorb the high bending loads, continuous steel plates are installed on the underside of the carriageways, which are firmly connected to the concrete using thousands of headed dowel pins. However, these "sheets" are by no means thin: with thicknesses of between seven and 14 centimetres and lengths of up to 157 metres, these are solid steel plates.


Without the Liebherr innovations VarioTray and V-Frame, the job would not have been possible.
Without the Liebherr innovations VarioTray and V-Frame, the job would not have been possible.

Heavy loads at lofty heights


Instead of welding the individual short plates onto the bridge - which would have blocked construction for weeks - they were welded into long steel plates on the ground in parallel with the other construction work, so that they could then be lifted as a whole. However, this increased the weight per element to up to 70 tonnes. To prevent the sheets from bending during lifting, they were attached to a lattice crossbeam. Including lifting gear, this resulted in loads of 85 and 102 tonnes, which had to be lifted from the valley onto the bridge being built at a height of 65 metres.


For this work, Wiesbauer used the LR 1700-1.0 with a 132 metre main boom, 12 metre fixed jib and up to 375 tonnes of ballast and the LTM 1650-8.1 with Y-guying, 155 tonnes of ballast, 16 metre telescopic extension and 38.5 metre luffing jib.


The LR 1700-1.0 was set up approximately in the centre of the valley directly in front of the bridge section where the heavier steel plates had to be mounted. This enabled the crane to cope with these loads on its own. For the positions further south, a tandem lift was necessary due to the larger radius, with the crawler crane working with the LTM 1650-8.1.

The LR 1700-1.0 first placed the 85-tonne load in an accessible position on the bridge, from where the two cranes jointly slewed it to its final position and set it down with millimetre precision.


Precise technology and millimetre-precise coordination


The combination of VarioTray and V-Frame made the LR 1700-1.0 a decisive tool in the cramped operating conditions: the ballast radius could be continuously adjusted between 13 and 21 metres, depending on the radius. With a small radius, even the small pallet of the VarioTray with 100 tonnes of ballast was sufficient in some cases.


"Without VarioTray and V-Frame, the job would not have been possible in this form," explains crane operator Ralf Paladey. "During the lift, we had to constantly adjust the ballast radius in order to maintain the exact balance." The lift placed the highest demands on the control system and the interaction between the two machines. During the tandem lift, the working radius of the crawler crane reached up to 96 metres.


Cramped conditions and logistical challenges


The assembly of the cranes also required logistical finesse. The location was in a narrow valley - the Neckar to the north and a railway line to the south. An alternative set-up was ruled out. All the components had to be reloaded onto 8-axle low-loaders in order to safely negotiate the winding roads to the crane site in the valley. "Even the assembly was precision work," reports Ralf Hofmann, driver of the LTM 1650-8.1. "When installing the luffing jib, we had just one metre of space to the end of the path." Positioning closer to the bridge was impossible - the projecting edge only left about one metre of clearance at the lift.


Narrow serpentines and cramped conditions were a challenge for the team and cranes.
Narrow serpentines and cramped conditions were a challenge for the team and cranes.

Wiesbauer had calculated various options, including the use of a more powerful crawler crane. "Our LR 11000 could have handled the load from the stand alone," says project manager Jochen Wiesbauer, "but the ballast radius would have required slewing over the river - and that wasn't possible." A larger mobile crane was also considered, as the LTM 1650-8.1 was working at its limit. However, the dimensions of the 9-axle LTM 1750-9.1 did not allow it to travel down into the valley.


To prevent the sheets from bending during lifting, they were attached to a lattice crossbeam.
To prevent the sheets from bending during lifting, they were attached to a lattice crossbeam.

Planning with system and experience


The deployment was planned using the Liebherr tool LICCON deployment planner and a CAD system to precisely simulate all movements and loads. Nevertheless, some of the work was left to experience - especially when fine-tuning the cranes in tandem operation.

"Experience is essential here," emphasises crane operator Tim Moll. "Not everything can be calculated in advance. It is crucial to have the right sense of proportion when picking up the load and positioning the ballast pallet." After several days of intensive work, all four plates were securely mounted - a success that combined precision, technology and teamwork.

Comments


bottom of page