top of page
Unbiased News Banner_edited.jpg
Crane Hub - Crane News

Crane Industry News Latest Global Updates, Lifts, Accidents
& Market Insights

Crane Hub Global delivers trusted crane industry news from job sites, ports, project locations, and markets worldwide covering heavy lifts, specialized transport, maritime cranes, equipment deliveries, safety and operations, workforce development, and key industry moves.

Global reach. Local impact. Powered by the industry’s largest social media community.

 

Updated daily by the Crane Hub Global editorial team.

CraneLife

Crawler Cranes Build 1,500 Foot Ocean Outfall at Myrtle Beach

  • Writer: Meagan Wood
    Meagan Wood
  • Aug 20
  • 11 min read

30 Second Takeaway


ALL Carolina Crane Rental of Wilmington has supplied a Manitowoc 14000 and Link Belt 248 HSL crawler crane for construction of a deepwater stormwater outfall at 24th Avenue North in Myrtle Beach, South Carolina. The cranes first built a temporary trestle extending over the Atlantic Ocean. They are now handling 84 inch prestressed concrete pipe sections weighing up to 55,000 pounds as the pipeline advances approximately 1,500 feet offshore beneath the seabed. The $40 million project will connect the ocean outfall to the city’s stormwater network, replace 11 existing beachfront discharge pipes and help reduce flooding in one of Myrtle Beach’s most affected areas.



Two Crawler Cranes Support Coastal Infrastructure Project


Two lattice boom crawler cranes are supporting construction of Myrtle Beach’s fifth deepwater ocean outfall. ALL Carolina Crane Rental supplied the equipment to marine contractor Manson Construction, which is completing the offshore works at 24th Avenue North.


The crawler crane package consists of:

  • A Manitowoc 14000

  • A Link Belt 248 HSL

  • A 110 US ton All Terrain crane used during assembly

  • Crawler mats forming the trestle travel surface

  • Supporting rigging and installation equipment


The cranes perform different but connected roles during the pipe installation process.

The Link Belt transports concrete sections from the beach staging point along the trestle. The Manitowoc then lifts each section from the working platform and lowers it into the ocean for installation.


84 Inch Pipeline Extends 1,500 Feet Offshore


The new outfall consists of 84 inch prestressed concrete pipe extending approximately 1,500 feet into the Atlantic Ocean. Once complete, the pipeline will connect with the municipal stormwater system and carry runoff farther offshore. The system is intended to replace 11 smaller stormwater pipes currently discharging across the beachfront.


Consolidating these pipes into a deepwater outfall will allow the city to manage stormwater through a larger underground system while removing discharge points from the beach.

The project also incorporates systems intended to collect debris and filter stormwater before it is released.


Outfall Targets a Flood Prone Area


The area around 24th Avenue North experiences recurring flooding during periods of heavy rainfall. Hotels, parking areas, streets and other low lying properties near the beachfront can be affected when the existing drainage network is unable to carry runoff away quickly enough.


Billy Madden, sales representative with ALL Carolina Crane Rental of Wilmington, said:

 “This part of the beach floods more than any other. There are hotel parking lots that get two to three feet of water every time it rains.”
“This outfall will mitigate the flooding by connecting to the storm sewer and carrying excess runoff deeper into the ocean.”

The project forms part of a wider programme of stormwater improvements along the approximately 60 mile Grand Strand coastline.


Cranes First Built Their Own Working Platform


Before installation of the concrete pipeline could begin, the cranes were used to construct a temporary trestle extending from the beach over the water. The trestle follows the planned route of the outfall and provides a stable working platform for the crawler cranes, pipe sections and construction crews.


The Link Belt 248 HSL arrived first and performed much of the structural work.

Its construction sequence included:

  • Driving sheet piles

  • Installing round pilings

  • Placing custom steel girders

  • Installing supporting structural components

  • Positioning crawler mats

  • Preparing the travel surface


Once the trestle was completed, both crawler cranes could travel above the ocean and advance with the pipeline installation.


Trestle Transfers Crane Loads Into the Seabed


The temporary structure must support more than the weight of the cranes.

It also carries the pipe sections, crawler mats, rigging and supporting construction equipment. Loads from the crawler tracks pass through the mats and steel framing before being transferred through the supporting piles into the seabed.


The trestle therefore had to be engineered for:

  • Crane operating weight

  • Suspended loads

  • Track loading

  • Travel loads

  • Boom configuration

  • Counterweight

  • Pipe storage

  • Construction equipment

  • Wave and current action

  • Wind loading

  • Tidal conditions


Crane movement along the structure also changes the position of the load applied to the trestle. Each stage of travel and lifting must remain within the approved structural and crane operating limits.


Manitowoc 14000 Handles the Heaviest Pipe Sections


The Manitowoc 14000 performs the principal pipe installation lifts.

For the Myrtle Beach project, the crane is configured with:

  • 164 feet of main boom

  • 221,000 pounds of counterweight

  • Capacity to handle pipe sections weighing up to 55,000 pounds


The crane lifts each concrete pipe section individually before lowering it below the waterline.

“We specified the 14000 for our customer, Manson Construction, because its higher capacity is better suited to the heavier concrete pipe sections,”

Madden said.


The selected boom and counterweight arrangement provides the capacity required at the project’s planned working radii. Actual lifting capacity depends on the crane’s configuration, boom angle, operating radius and applicable load chart.


Manitowoc 14000 Technical Overview


The Manitowoc 14000 is a lattice boom crawler crane with a maximum rated capacity of 220 US tons, equivalent to approximately 200 tonnes. The crane can be configured with a main boom extending to approximately 292 feet, or 89 metres.


Additional attachment options include:

  • Fixed jibs up to 80 feet

  • Luffing jibs up to 170 feet

  • Maximum boom and luffing jib combinations reaching approximately 364 feet

  • Multiple boom configurations for different capacity and reach requirements


The Model 14000 incorporates Manitowoc’s EPIC control system with CAN Bus communication and six independent closed loop hydraulic circuits. Its FACT connection system is designed to support crane assembly and disassembly.


The complete crane, including its maximum boom, fixed jib and counterweight package, can be transported across approximately 12 truckloads, depending on configuration and regional transport requirements.


Link Belt 248 HSL Feeds Pipe Along the Trestle


The Link Belt 248 HSL remains on the project as the material handling crane for the pipe installation sequence. Concrete sections arrive by road on flatbed trailers and must then be transferred from the beach access area to the Manitowoc’s operating position.

The Link Belt lifts each pipe section from the delivery area and carries or relays it along the trestle.


For this work, it is configured with:

  • 155 feet of main boom

  • 168,000 pounds of counterweight

  • Lattice boom suited to repeated material handling

  • Crawler undercarriage for movement along the trestle

Separating transport and installation duties allows the Manitowoc to remain in position for the critical subsea lifts while the Link Belt maintains the supply of pipe. This helps avoid repeatedly moving or reconfiguring the primary installation crane.


Link Belt 248 HSL Technical Overview


The Link Belt 248 HSL has a manufacturer listed base capacity of 200 US tons at a 12 foot radius, equivalent to approximately 181 tonnes at 3.7 metres. Its lattice main boom can be configured from 55 to 285 feet, or approximately 16.8 to 86.9 metres.


Available fixed jib lengths range from 30 to 100 feet, with offset positions of 5, 15 and 25 degrees.


The crane provides:

  • Maximum fixed jib tip height of approximately 348.4 feet

  • Cummins QSB6.7 Tier 4 Final engine

  • Maximum hoist pull of approximately 46,924 pounds

  • Maximum line speed of approximately 502 feet per minute

  • Full chart 360 degree pick and carry capability

  • Adjustable operating speeds

  • Function slowdown and stop limits

  • Self assembly features


For the Myrtle Beach work, the crane’s crawler undercarriage and pick and carry capability are important because pipe sections must be moved along the narrow trestle.


Two Crane Workflow Separates Transport and Installation


The project uses the cranes as a coordinated material handling system. The Link Belt is responsible for moving pipe from the beach staging area towards the installation point. The Manitowoc then completes the final lift into the ocean.


The sequence involves:

  1. Delivering the pipe to the beach access area

  2. Unloading it with the Link Belt

  3. Moving the section along the trestle

  4. Transferring it to the Manitowoc’s working area

  5. Connecting the installation rigging

  6. Lifting the pipe from the trestle

  7. Lowering it below the surface

  8. Positioning it inside the setting box

  9. Connecting it to the installed pipeline

  10. Releasing and recovering the rigging


This division of work allows pipe delivery and installation activities to continue without requiring one crane to perform every stage.


Steel Setting Box Protects the Pipe During Installation


Once the Manitowoc lowers a pipe section below the surface, it is positioned inside a specially fabricated steel setting box. The box protects the pipe from lateral movement caused by ocean currents while divers complete the connection.


Without this protection, water movement could shift the suspended section and make accurate alignment with the previously installed pipe more difficult. The setting box creates a more controlled installation area around the joint. The crane continues to support and position the pipe while the dive team confirms alignment.


Divers Complete the Underwater Connections


Manson Construction divers work beneath the surface to guide the concrete pipe sections together.


The operation requires close communication between:

  • Crane operators

  • Lift supervisors

  • Divers

  • Dive supervisors

  • Rigging personnel

  • Trestle crews

  • Survey personnel


The crane operator cannot directly see the final connection point, making communication and monitoring essential. The dive team guides the suspended section into alignment while the Manitowoc makes controlled lifting and lowering movements. Underwater visibility, ocean currents and changing sea conditions can all affect the installation process.


Wedge Lock Joint Secures Each Pipe Section


The 84 inch pipe sections use a wedge lock joint system. Once the ends of two sections are aligned, the connection mechanically locks them together to form the continuing pipeline.


The joint must resist movement and loading generated by:

  • Ocean currents

  • Wave action

  • Seabed conditions

  • Pipeline weight

  • Stormwater discharge

  • Settlement

  • Long term marine exposure


The setting box keeps the pipe stable while the divers complete the joint.

After the connection is confirmed, the lifting equipment can be disconnected and recovered to the trestle.


Concrete Replaces Smaller CPVC Pipe


Previous outfall projects in the area used 54 inch chlorinated polyvinyl chloride pipe.

The 24th Avenue North system uses larger and heavier 84 inch prestressed concrete sections. The increased diameter provides greater flow capacity, but it also changes the lifting requirements. Concrete pipe sections weighing as much as 55,000 pounds require a larger crane, suitable rigging and a trestle designed for the increased load.

The Manitowoc 14000 was selected specifically to provide the capacity needed for these heavier sections.


Crane Assembly Completed Through 50 Foot Beach Access


The two crawler cranes were assembled at a public beach access point only approximately 50 feet wide. Crawler cranes are transported in multiple loads, including the carbody, tracks, boom sections, counterweights, hook blocks and other components.


The narrow access area provided limited room for:

  • Delivery trucks

  • Crane components

  • Assembly operations

  • Support equipment

  • Counterweight installation

  • Boom assembly

  • Personnel access


A 110 US ton All Terrain crane assisted with the assembly because the crawler cranes could not assemble themselves easily within the restricted area.

“The beach access was extremely narrow, so every step had to be carefully coordinated,”

Madden said.


Components Delivered From Remote Laydown Yard


The main laydown yard was located approximately five to eight miles from the beachfront site. Crane components, crawler mats, pipe sections and construction materials could not be stored together at the beach because of the limited staging area.

Instead, each item had to be transported to the site in the order required.


This created a controlled delivery schedule covering:

  • Crane components

  • Boom sections

  • Counterweights

  • Crawler mats

  • Steel trestle elements

  • Concrete pipe sections

  • Rigging

  • Support equipment


Delivering too many components at once could block the access point and prevent assembly or lifting operations from continuing.


Beach Construction Adds Environmental Challenges


Coastal crane operations are affected by environmental conditions that differ from those at a conventional land based construction site.


The project team must consider:

  • Tides

  • Wave action

  • Ocean currents

  • Wind speed

  • Saltwater exposure

  • Sand movement

  • Seabed conditions

  • Storm systems

  • Corrosion

  • Public beach access


The cranes operate from an engineered trestle rather than directly from the beach or seabed. Daily planning must account for changes in weather and sea conditions before pipe installation begins.


Project Represents a $40 Million Investment


The City of Myrtle Beach identifies the 24th Avenue North outfall as a $40 million infrastructure project. The city received $30 million in state funding towards the programme, along with additional funding connected with stormwater outfall work.


The project is expected to:

  • Replace 11 beachfront drainage pipes

  • Improve stormwater collection

  • Reduce flooding

  • Carry runoff farther offshore

  • Improve beach conditions

  • Support water filtration and debris collection

  • Protect surrounding properties and infrastructure

The outfall is Myrtle Beach’s fifth deepwater ocean discharge project.


Continuing Partnership Between ALL and Manson


The project continues a working relationship between ALL Carolina Crane Rental and Manson Construction. ALL Carolina has supplied cranes for several ocean outfall projects along the Grand Strand. Manson provides marine construction experience covering pile driving, trestle construction, diving and subsea installation.


The combination of crawler crane capacity and marine construction expertise allows the companies to complete lifting operations extending from the beach to the offshore installation point.


About ALL Carolina Crane Rental


ALL Carolina Crane Rental of Wilmington is a crane rental and lifting services company based in Rocky Point, North Carolina. The business became a dedicated member of the ALL Family of Companies in 2007 and supports customers across North Carolina and surrounding markets.


Its services cover crane rental, operated lifting, equipment supply, project planning and technical support for construction, industrial, infrastructure and marine projects.

ALL Carolina can also draw equipment and personnel from the wider ALL Family fleet.


Company website: www.allcrane.com


About the ALL Family of Companies


The ALL Family of Companies was founded in Cleveland, Ohio, in 1964 by brothers Michael, Jake and Larry Liptak with a single crane. It has developed into a network of crane rental, sales and service businesses operating across North America.


The family owned company employs approximately 1,500 people and provides:

  • Mobile crane rental

  • Crawler crane rental

  • Tower cranes

  • Boom trucks

  • Aerial equipment

  • Material handling equipment

  • Equipment sales

  • Parts and maintenance

  • Lift planning

  • Transport and logistics support


The group supports construction, industrial, energy, infrastructure, manufacturing and specialised lifting projects.


Company website: www.allcrane.com


About Manson Construction


Manson Construction is a United States marine construction, dredging, offshore and heavy lifting contractor. The company was founded in 1905 as a small pile driving business supporting development of the Seattle waterfront.

It has since expanded across North America, employing more than 800 people and operating a fleet of marine construction equipment.


Manson’s services include:

  • Marine construction

  • Dredging

  • Offshore work

  • Heavy lifting

  • Pile installation

  • Waterfront infrastructure

  • Subsea construction

  • Bridge and terminal projects



About Manitowoc


The Manitowoc Company manufactures cranes under the Manitowoc, Grove, Potain and National Crane brands. Its Manitowoc product line specialises in lattice boom crawler cranes used across infrastructure, energy, industrial, marine and heavy construction projects.

The Model 14000 is a previous generation 220 US ton crawler crane offering multiple main boom, fixed jib and luffing jib configurations.


Company website: www.manitowoc.com

Manitowoc 14000 product page: Manitowoc 14000


About Link Belt Cranes


Link Belt Cranes manufactures rough terrain, All Terrain, truck, telescopic crawler and lattice boom crawler cranes at its facility in Lexington, Kentucky.

The company supplies cranes for construction, infrastructure, energy, industrial and material handling applications. The Link Belt 248 HSL is a 200 US ton class lattice boom crawler crane designed for lifting and pick and carry work.


Company website: www.linkbelt.com

248 HSL product page: Link Belt 248 HSL


Frequently Asked Questions


Where is the stormwater outfall being installed?

The pipeline is being installed at 24th Avenue North in Myrtle Beach, South Carolina.


How far does the pipeline extend offshore?

The outfall extends approximately 1,500 feet into the Atlantic Ocean.


What size pipe is being installed?

The project uses 84 inch prestressed concrete pipe.


How much does the heaviest pipe section weigh?

The heaviest sections weigh approximately 55,000 pounds, or 24.9 tonnes.


Which cranes are working on the project?

ALL Carolina supplied a Manitowoc 14000 and a Link Belt 248 HSL lattice boom crawler crane.


What is the Manitowoc 14000’s capacity?

The Manitowoc 14000 has a maximum rated capacity of 220 US tons, equivalent to approximately 200 tonnes.


What is the Link Belt 248 HSL’s capacity?

Link Belt lists the 248 HSL at 200 US tons, equivalent to approximately 181 tonnes.


What does the Link Belt crane do?

The Link Belt moves pipe sections from delivery trailers along the temporary trestle to the installation area.


What does the Manitowoc crane do?

The Manitowoc lifts each pipe section from the trestle and lowers it beneath the ocean surface.


Why was a temporary trestle required?

The trestle provides a stable platform that allows the crawler cranes to travel and work approximately 1,500 feet offshore.


How are the pipe sections connected?

Divers align and connect the sections underwater using a wedge lock joint system.


What is the steel setting box used for?

The box protects the pipe from ocean currents and provides a controlled area for alignment and connection.


How much does the project cost?

The City of Myrtle Beach lists the project cost at approximately $40 million.


What will the new outfall replace?

It will replace 11 existing stormwater pipes discharging across the beachfront.

Your daily source for global crane industry news, heavy lift projects, and equipment updates.

Today’s top crane industry news worldwide

Do you have Crane News?

Liebherr Cranes

Reach Out To Our Editorial Team!

We invite you to connect with the Crane Hub editorial team to share your news, content, or press releases. Your insights and stories are valuable to us, and we believe they can enrich our community. Don't hesitate to reach out and let us know how we can collaborate to bring your message to a wider audience. Together, we can highlight the stories that matter most!

Explore the Crane Hub News Archive for more global crane and heavy lift coverage.

Related Topics
 

Click a tag to discover more crane industry coverage

Magazines Banner.png

Stay Ahead of the Lift

Subscribe to Crane Hub for global crane industry news, insights, and stories about people shaping lifting worldwide

One Subscription. Total Industry Visibility

Crane Hub Global is the industry’s leading multi-media platform for the crane, lifting, and heavy equipment industry. As the largest digital media hub and social community in the crane sector, we deliver trusted crane industry news, digital magazines, podcasts, video content, and global event reporting.

 

Our platform connects crane operators, fleet owners, OEMs, contractors, and lifting professionals with the latest technology, safety developments, and expert insight shaping modern crane and heavy lift operations worldwide.

 

Crane Hub Global is the crane industry’s most powerful source for real-time information, media, and marketing  all in one place.


Crane Industry Media Engine

Crane Industry News

Crane Hub Global Magazines are leading crane industry publications covering cranes, lifting operations, heavy equipment, and specialized transport worldwide. Each issue delivers expert insight, market trends, and real-world reporting for crane operators, engineers, fleet owners, and industry leaders.

Crane Industry News

The Lift Point Podcast is Crane Hub Global’s leading crane industry podcast, featuring the stories, strategies, and voices shaping the global crane, lifting, and heavy equipment sectors. Each episode brings industry leaders, innovators, and experts together to discuss crane safety, new technology, workforce challenges, and real-world lift operations.Designed for crane professionals worldwide, The Lift Point delivers essential insight and conversation for anyone looking to stay informed and ahead in the lifting industry.

Crane Industry News

Booms Up Buzz is Crane Hub Global’s fast-moving source for crane industry news, equipment innovations, and lifting market updates. Built for busy crane and heavy equipment professionals, it delivers quick, focused coverage of the trends, technology, and stories shaping the global lifting sector. Each edition cuts through the noise with clear, actionable insight  your essential pulse check on what’s buzzing across cranes, heavy lift, and specialized transport.

Crane Industry News

Crane Hub Global’s social media channels deliver real-time crane industry news, lifting updates, and heavy equipment coverage from across the global market. With the largest social media following in the crane sector, we connect operators, OEMs, contractors, and industry leaders to the stories, trends, and innovations shaping modern lifting operations.

Crane Industry News
bottom of page