Titschkus & Wittrock’s New Liebherr LTM 1250-5.1 Takes First Lift Under Bremen Stadium Roof

30-Second Takeaway
The football pitch was off limits and the East Stand roof restricted headroom on the first job for Titschkus & Wittrock’s new 250-tonne Liebherr LTM 1250-5.1. At Werder Bremen’s Weserstadion, the crew installed steelwork and around 10 precast concrete elements between match days. The heaviest sections weighed approximately eight tonnes, and the lifts reached a maximum working radius of about 32 metres.
Placing precast concrete beneath the Ostkurve roof
The Bremen crane and transport company put its new five-axle all-terrain crane straight to work on Block 53 in the stadium’s Ostkurve, or East Stand. The crew first lifted steel beams into the damaged section, followed by the replacement concrete elements.
Part of the installation took place beneath the existing grandstand roof. That left little room above the components for rigging and limited how the operator could approach the final placement. The crew used short slings to reduce the headroom needed between the hook and the load. For some placements, the operator telescoped the boom under load to move the component into position beneath the roof.
The pitch also had to remain untouched throughout the work. With little room inside the stadium to stage steel and concrete, deliveries followed the installation sequence. Each component arrived when the crew needed it, keeping the available space clear for the next lift before the following match day.
What damaged Block 53 at the Weserstadion?
Werder Bremen reported the original incident on 8 July 2026. During modernisation work, a load-bearing column was accidentally damaged while window panes were being removed from a VIP area. Part of the upper tier of Block 53 subsequently collapsed.
No one was injured. Stadium management reported that the adjacent sections were unaffected. Titschkus & Wittrock’s assignment was part of the subsequent reconstruction of the damaged stand.
Liebherr LTM 1250-5.1 crane specifications
The LTM 1250-5.1 carries a six-section, 60-metre telescopic main boom on a five-axle carrier. Its swingaway extension can reach 36 metres, or 50 metres with inserts, and offers hydraulic offset of up to 45 degrees.
At the Weserstadion, the critical dimension was the space available beneath the roof. The crane’s ability to change boom length while carrying a component gave the operator a way to complete the final approach within that space.
About Titschkus & Wittrock
Titschkus & Wittrock GmbH & Co. KG is a Bremen-based crane rental and transport company within the Wittrock Group. Its Bremen operation supplies mobile cranes, access platforms and forklifts and provides heavy transport services. The Weserstadion repair was the first assignment for its new 250-tonne Liebherr all-terrain crane.
About Liebherr
Liebherr manufactures mobile and crawler cranes for construction, industrial assembly and heavy lifting. Its LTM all-terrain range combines a road-going carrier with a telescopic boom. The LTM 1250-5.1 is the manufacturer’s 250-tonne, five-axle model, with boom extension options for work requiring additional reach or an offset jib.
Website: https://www.liebherr.com/
Frequently Asked Questions
What was the first job for Titschkus & Wittrock’s new Liebherr LTM 1250-5.1?
The crane helped rebuild part of Block 53 in the East Stand at Werder Bremen’s Weserstadion. The crew installed replacement steelwork and precast concrete elements.
How heavy were the concrete sections lifted at the Weserstadion?
The heaviest precast sections weighed approximately eight tonnes each. Around 10 concrete elements were installed after the steelwork.
What did the 32-metre figure refer to on the stadium lift?
Liebherr reported a maximum working radius of approximately 32 metres. That describes the horizontal distance from the crane’s centre of rotation to the load. Liebherr reported the heaviest load and the longest radius separately.
Why did the crew use short slings under the grandstand roof?
The roof restricted the vertical space available for rigging. Short slings reduced the distance needed between the hook and the component, leaving more clearance for placement.
How did the operator position loads beneath the stadium roof?
For some placements, the operator extended the telescopic boom while carrying the component. This allowed the crew to move the load into its final position within the confined area.
How did the match schedule affect the crane work?
The installation had to fit between two match days. With the pitch out of bounds and little storage space in the stadium, steel and concrete deliveries were timed to match the lifting sequence.